Lake Tansi POA Latest Status & Updates on Ongoing Projects


June, 2008
Re: Capital Improvements Project Update

Cabins

We now have TEN of our new cabins completed and renting. The remaining two are framed, roofed, and partially completed inside. Siding and the remainder of the inside work should be completed by July 4th or very shortly thereafter. The parking area has been expanded and temporary paving on the west side of the site is complete.

The open house was well received and we heard nothing but positive comments not only from our members but from visitors who came through.

Maintenance Building

Material storage bins are being completed as of this writing. The interior work on the building is at 80 % complete. We are waiting for the electric company to set poles and run in the overhead electric lines. The underground water and gas lines are in place and final connections will proceed once power is delivered to the building.

Final grading and paving is scheduled for the week of July 7th and should be completed by the end of that week, weather permitting.

Membrane Plant

Unfortunately we are still awaiting documentation from the State on our permit application. Thus, there is no progress to report at this time.

T-Bird/Outdoor Pool

We have not reported on this phase of the projects before. But—there has been updating of the electrical system completed in the T-Bird and all the repairs to the outdoor pool have been completed. This work was part of the original plan and was packaged with the proposed new indoor pool. We are very pleased to report that the outdoor pool repairs were completed at some $33,000.00 under budget. A very nice savings indeed.

Respectfully submitted,

Capital Improvement Committee